Introduction

These guidelines are to ensure that operations can cleanly take place at any time of the day.

Equipment/physical

  • No cable ever touches the ground
    • Protecting against stepping on and possible water entrance in case of physical disaster
  • All production servers are connected to the grid only by means of a UPS
    • To avoid over/under voltage issues
    • To keep them running in case of power outage
  • No mix of production and development equipment
    • At the end of each working day, all production areas must be completely cleaned up