closed

Our switches in place8 should be moved to a different location / rack

Added by Nico Schottelius over 4 years ago. Updated over 3 years ago.

Status:
Closed
Priority:
Normal
Target version:
-
Start date:
10/21/2019
Due date:
10/30/2019
% Done:

0%

Estimated time:
PM Check date:

Description

  • Coordinate with Kilian Bäbler
  • Visit place8 once before doing the actual move
    • Checkout the UPS situation
    • Verify that both switches are connected to the UPS
    • Verify that the UPS can hold power for both switches

Step

  • First verify that the switches are both configured the same
  • First move the unused switch / the one that does not bridge the two data centers
  • Then move the cables to the moved switch (-> short interrupt between the data centers)
    • Have 1 or 2 notebooks open, testing the connection
    • Verify that connection is back when plugging back in
  • Then move the second switch (which is now the backup switch

Should be finished by mid next week.

Actions #1

Updated by Nico Schottelius over 4 years ago

  • Description updated (diff)
  • Due date set to 10/30/2019
Actions #2

Updated by Samuel Hailu over 3 years ago

  • Status changed from New to Resolved
  • Assignee changed from Samuel Hailu to Nico Schottelius
Actions #3

Updated by Nico Schottelius over 3 years ago

  • Status changed from Resolved to Closed
Actions