Task #7284

closed

router1.place6 phase back in

Added by Nico Schottelius over 4 years ago. Updated 3 months ago.

Status:
Closed
Priority:
Normal
Target version:
-
Start date:
01/02/2020
Due date:
% Done:

100%

Estimated time:
(Total: 0.00 h)
PM Check date:

Description

Step 1: routing setup

  • Accept all networks from upstreams and ungleich peers
  • don't announce any network
  • full routing table in kernel
  • no ip hacks (dummy0, lo)
  • do we still need to solve the "next hop self ebgp;" problem with bird2?
    • bird2 will reject announcements from routerX peers in ungleich
    • bird2 will accept announcements from upstreams (direct)
    • bird2 to bird2 will accept due to rewrite
  • Announcing 2a09:2942::/32 only via netstream makes it unreachable
    • Announcing it to router1.place5 makes it instantly reachable

At this stage the router is fully able to do IPv4 and IPv6 routing

Step 2: add some traffic

  • add the IPv6 address of the coworking network -> go active-active

Step 3: add nat64 w/ jool + joold

  • setup jool+joold for "masquarding" 1:n sessions to .1 IPv4 address

Step 4: Announce test network (IPv4, IPv6)

  • Something non-productive
  • ensure routing works
  • Maybe spin up VMs and/or end hosts in that network

Step 5: announce all networks to upstreams and peers

  • final step for back in production
  • at this point router2.place6 can be reinstalled/replaced
    • repeat all steps from here

Subtasks 2 (0 open2 closed)

Task #7552: Add some non-critical traffic to router1.place6ClosedNico Schottelius01/02/2020

Actions
Task #7553: Setup conntrackd to allow active active firewallsRejectedTimothée Floure01/02/2020

Actions

Related issues 1 (0 open1 closed)

Related to Open Infrastructure - Task #7306: Phase in new routersRejectedNico Schottelius11/09/2019

Actions
Actions #1

Updated by Nico Schottelius over 4 years ago

  • Description updated (diff)
Actions #2

Updated by Nico Schottelius over 4 years ago

  • Description updated (diff)
Actions #3

Updated by Nico Schottelius over 4 years ago

  • Description updated (diff)
Actions #4

Updated by Nico Schottelius about 4 years ago

  • Related to Task #7306: Phase in new routers added
Actions #5

Updated by Nico Schottelius 3 months ago

  • Status changed from In Progress to Closed
Actions

Also available in: Atom PDF