Task #6557

closed

Rebuild the whole DCL infrastructure - aka place9

Added by Nico Schottelius over 5 years ago. Updated about 4 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Target version:
-
Start date:
04/01/2019
Due date:
06/27/2019
% Done:

100%

Estimated time:
(Total: 0.00 h)
PM Check date:
04/10/2019

Description

As a part of our process to ensure stability and find bugs in our infrastructure, we will create a clone of our data center with new hardware, net networking, new routing - basically new everything.

The data center should be rebuilt by:

  • Nico (giving very rough directions)
  • Jason (leading the process)
  • On site / system engineering
    • Sami
    • Roli
    • Marc
  • Off-site system engineering
    • Jin-Guk

Subtasks 14 (0 open14 closed)

Task #6559: Understand the current networking infrustructure of place6ClosedSamuel Hailu04/01/2019

Actions
Task #6582: Setup the first routerClosedll nu04/10/2019

Actions
Task #6600: Configure and define upstream networkingClosedNico Schottelius04/16/2019

Actions
Task #6601: Setup the arista switches at place6-east and place9Closedll nu04/16/2019

Actions
Task #6632: Setup all servers physically and BIOS / idracClosedMarc Auer04/29/201905/09/2019

Actions
Task #6648: Configure (reset cleanly) a Mikrotik hapAC as a fiber2copper bridge, connect all servers with copperClosedSamuel Hailu05/01/2019

Actions
Task #6649: Create new internal VLAN for place9 WITH a router and move servers to the internal VLANClosedSamuel Hailu05/01/2019

Actions
Task #6650: Make Mikrotik a router for the fiber network, enable the server network (vlan), use vlan tagging on the mikrotik to be able to be a routerClosedSamuel Hailu05/01/2019

Actions
Task #6651: The network documentation ticketClosedNico Schottelius05/01/2019

Actions
Task #6652: Install 2 Linux routers with Alpine LinuxClosedSamuel Hailu05/01/2019

Actions
Task #6709: Configure IPv6 only netbootingClosedSamuel Hailu05/20/2019

Actions
Task #6725: Order new hardware for place9ClosedNico Schottelius05/23/2019

Actions
Task #6873: Ensure that all new 9 servers are running by end of weekRejectedSamuel Hailu06/23/201906/27/2019

Actions
Task #6946: Setup the other side of the arista switchesClosedll nu07/10/2019

Actions