Task #6557
closedRebuild the whole DCL infrastructure - aka place9
Start date:
04/01/2019
Due date:
06/27/2019
% Done:
100%
Estimated time:
(Total: 0.00 h)
PM Check date:
04/10/2019
Description
As a part of our process to ensure stability and find bugs in our infrastructure, we will create a clone of our data center with new hardware, net networking, new routing - basically new everything.
The data center should be rebuilt by:
- Nico (giving very rough directions)
- Jason (leading the process)
- On site / system engineering
- Sami
- Roli
- Marc
- Off-site system engineering
- Jin-Guk